Licensed Items: Design the Approval Path Early

  • Haider Syed
  • Dec 17, 2025
  • 1 min read

Licensed or controlled requirements fail when the process is discovered late.

You don’t “solve licensing” after selecting a supplier. You design a path early:

  • Who owns approvals?

  • Which documents are mandatory?

  • What are the lead times for each review step?

  • Which channel is permitted (approved route, authorized parties)?

  • What triggers a hold?

A practical structure:

  1. Identify early: mark the requirement as licensed/controlled at inquiry stage

  2. Define responsibility: one owner for approvals + one owner for document control

  3. Build the document list: minimum set needed to start reviews

  4. Sequence the timeline: approvals should run parallel with procurement work, not after

  5. Track gates: no dispatch until the “license-ready” checklist is green

The goal is not to “rush.” The goal is to avoid a late-stage stop when everyone assumes it will “work out.”

Takeaway: Licensed items are predictable if you map the approval path before RFQ—roles, documents, gates, and timing.

 
 
 